PROJECT OVERVIEW

CLIENT
FI Real Estate Management Ltd

LOCATION
Friars House, Coventry

MARKET SECTOR
Commercial

ANDERTON GABLES ROLES
Designer
Contract Administration
Project Management
Principle Designer

KEY COMPANIES
N/A

PROJECT VALUE
£928, 000.00

PROJECT COMMENCEMENT DATE
January 2017

PROJECT DURATION
15 Weeks

PROJECT SIZE
Refurb 3 Floors out of a 10 storey office building

Contact Us

Project Brief

+

Following the purchase of the building by FI-REM, Anderton Gables were appointed to undertake CAT A Strip Out and Formation of Serviced Offices.

Image module

Project Summary

+

The works comprised of;

  • New ceiling and lighting to ground floor reception,
  •  Formation of Serviced Offices to 4th Floor,
  • New welfare/kitchen/break out areas to 4th, 8th & 9th Floors,
  • CAT A Strip Out and Refurbishment of 8th & 9th Floors,
  • Refurbishment of Lift Lobbies and Access Corridors,
  • Refurbishment of Accessible WC, Female and Male
    Washrooms to 4th, 8th and 9th Floors,
  • Formation of a Shower Room to the 8th Floor,
  • Working in conjunction with M&E Consultants. Providing new
    lighting, heating/cooling, data, BMS System etc.