Dunnerdale Close

Preston, Lancashire

PROJECT OVERVIEW

CLIENT
Community Gateway Association

LOCATION
Preston

MARKET SECTOR
Housing

ANDERTON GABLES ROLES
Employers Agent
Clerk of Works

KEY COMPANIES
Galliford Try Plc
Community Gateway Association

PROJECT VALUE
£3 million

PROJECT COMMENCEMENT DATE
March 2014

PROJECT DURATION
52 Weeks

PROJECT SIZE
34 No. New Build Units

Project Brief

+

Galliford Try Plc agreed to develop a former North West Water Depot Site on the outskirts of Preston which had remained vacant for a number of years.

Anderton Gables were appointed as Employers Agent to assist in delivering the 34-unit scheme designed to achieve Code for Sustainable Homes – Level 4 (the largest scheme to be developed by the Association to date).

Image module

Project Summary

+

Anderton Gables Employers Agents instructed a full ground investigation report of the site along with asbestos surveys of the existing buildings.

Anderton Gables Employers Agents produced all documentation in relation to the Employers Requirements and audited the Contractors Proposals prior to preparing the formal JCT Design and Build Contract. Anderton Gables Employers Agents have then monitored works onsite, chaired progress meetings, provided monthly progress and financial statements and liaised with the different parties involved to ensure that the Employers Requirements are being met.

Anderton Gables also provided CDM-C services and latterly a Clerk of Works services to provide a ‘one stop’ multi-disciplinary service for the Association, and to ensure that the scheme achieved completion by March 2015.